Project Schedule |
Date | Descirption |
8/29-9/15 | Theoretical Calculation and Research |
9/15-10/25 | Experiment Design and Optical Design Reiterations |
10/26-11/22 | Computer Hardware Interface |
11/23-12/09 | Final Design/Report (Ordering Parts) |
12/09-2/15 | Construction, Electronics and Optical Layout |
1/4-1/10 | Horizontal Stage, Dectector/Data Acquisition System |
1/11-1/18 | Gating Mount and Support, Motor Electrical System |
1/19-1/26 | Motor Guides, Assemble Linear Motor System, General Electrical |
1/26-2/1 | Spectrograph Case and Lens PVC Mounts, Computer Interface |
2/2-2/9 | Spectrograph Case Legs, Validate Electrical System |
2/10-2/15 | Wiggle Room, Finalize Computer Interface and Functionality |
2/15-3/1 | Testing / Calibration |
3/2-4/15 | Implementation - Performing experiments and analyzing results |
4/15-5/4 | Final Report/Presentation |
5/16-5/19 | NSSSC Final Competition! |