Project Schedule |
| Date | Description |
| 8/29-9/15 | Theoretical Calculation and Research |
| 9/15-10/25 | Experiment Design and Optical Design Reiterations |
| 10/26-11/22 | Computer Hardware Interface |
| 11/23-12/09 | Final Design/Report (Ordering Parts) |
| 12/09-3/15 | Construction, Electronics and Optical Layout |
| 1/11-1/18 | Gating Mount and Support, Motor Electrical System |
| 1/26-3/15 | Spectrograph Case and Lens PVC Mounts, Computer Interface |
| 2/2-3/15 | Spectrograph Case Legs, Validate Electrical System |
| 3/1-4/1 | Horizontal Stage, Dectector/Data Acquisition System |
| 3/1-4/1 | Motor Guides, Assemble Linear Motor System, General Electrical |
| 4/1-4/26 | Finalize Computer Interface and Functionality |
| 4/15-4/26 | Testing / Calibration |
| 4/15-5/18 | Implementation - Performing experiments and analyzing results |
| 4/15-4/30 | Final Report/Presentation |
| 5/16-5/19 | NSSSC Final Competition! |