Fall Schedule:
Project Task | Estimated Time | Responsible |
Final Design Report Due | 12/4/2012 | Dain Vermaak |
Stream HSMC data to Eclipse output display | Jan 2013 | Dain Vermaak |
Capture HSMC output for given time period | Jan 2013 | Dain Vermaak |
Run search for sync bit on HSMC binary output | Jan 2013 | James Tasker |
Mark Sync bit in real-time | Jan 2013 | James Tasker |
Synchronize with system clock in order to display on VGA | Jan 2013 | Dain Vermaak |
Repair VGA color tables | Jan 2013 | Dain Vermaak |
Product Readiness Review | Feb 2013 | James Tasker |
Prove that Calibration works on the Cyclone IV | Feb – March 2013 | Dain Vermaak |
Implement Calibration Algorithm | Feb – March 2013 | James Tasker |
System Testing and Troubleshooting | March – April 2013 | James Tasker |
Document Compilation | March – April 2013 | Dain Vermaak |
Design Specifications 2 Implementation | March – April 2013 | Dain Vermaak |
Product Rollout | April 2013 | James Tasker |
Spring Design Fair | April 29 | James Tasker |