Fall Schedule:
| Project Task | Estimated Time | Responsible |
| Final Design Report Due | 12/4/2012 | Dain Vermaak |
| Stream HSMC data to Eclipse output display | Jan 2013 | Dain Vermaak |
| Capture HSMC output for given time period | Jan 2013 | Dain Vermaak |
| Run search for sync bit on HSMC binary output | Jan 2013 | James Tasker |
| Mark Sync bit in real-time | Jan 2013 | James Tasker |
| Synchronize with system clock in order to display on VGA | Jan 2013 | Dain Vermaak |
| Repair VGA color tables | Jan 2013 | Dain Vermaak |
| Product Readiness Review | Feb 2013 | James Tasker |
| Prove that Calibration works on the Cyclone IV | Feb – March 2013 | Dain Vermaak |
| Implement Calibration Algorithm | Feb – March 2013 | James Tasker |
| System Testing and Troubleshooting | March – April 2013 | James Tasker |
| Document Compilation | March – April 2013 | Dain Vermaak |
| Design Specifications 2 Implementation | March – April 2013 | Dain Vermaak |
| Product Rollout | April 2013 | James Tasker |
| Spring Design Fair | April 29 | James Tasker |