Future Work Plan
Table 3 shows the spring schedule for the project. These are dates that have been setup to meet to be able to finish the project. As the driven trolley is not part of the main projects, the project is done when the trolley is able to unweight someone and move across the I-beam. Therefore, February 10th is the date that is set to meet all the requirements and continue to develop the motion control. April 7th is the date set to finish the project.
December 15th |
January 10th |
January 27th |
February 10th |
March 10th |
April 7th |
Parts ordered |
Trolley Plates made |
Trolley built |
Able Unweight |
Trolley moved by arduino |
Movement control functions |
Side Supports ordered |
Trolley pulleys made |
Interface Circuit Built |
Trolley Functions as Trolley |
Testing control of movement |
Project is done |
Received all ordered parts |
Arduino control valve |
HI Finished |
|||
Motor decision |
Requirement met |
||||
Air piston mounted |
Begin Motor Control |
Table 3: Spring Schedule