Timeline for Fall of 2016

Timeline for Fall Semester of 2016

The current timeline for the Fall Semester of 2016 is going according to plan. As of December 12, the Design Journal, Final Design Report and Finalized design schematics are completed and awaiting approval from course advisor Andy Olson. The final schematic designs can be found in their respective sub-system pages. 

 

Projected Timeline for Spring of 2017

Projected Timeline for Spring Semester of 2017

For Spring of 2017 the timeline has system integration being complete by the beginning of April, with in-field testing starting sometime following this. The team sponsor, Mike Lance, is currently assessing potential testing locations, with the top candidate being within city limits somewhere along the Bozeman Creek. A prime location will be vital in the accessibility of testing as most other potential sites will require a minimum drive of two hours to reach. PCB design is anticipated to be complete within the following weeks, allowing for up to one month of purchase and delivery of the PCB.