Milestones
The milestones and their corresponding dates set forth by the ECEbot Power Upgrade team for the Fall 2006 semester are:
-
Build converter circuit on protoboard and test for project specifications.
Septermber 29th
-
Build the over-voltage protection circuit and test for specifications.
October 11th
-
Build the under-voltage protection circuit and test.
October 20th
-
Combine modules and test final prototype.
November 3rd
-
Create a PCB layout and arrange for fabrication of the board.
November 8th
-
Assemble final prototype with PCB and test for specification compliance.
November 27th
We feel that these milestones will provide us with a good measure of our project status throughout the following semester and will help keep us on track until our project’s completion.
|